A9 Tomatin to Moy - Lane Closures and Contraflow

Location

A9 between Tomatin and Moy project corridor and approximately 1km ahead of Moy at the northern end and 3km before Tomatin at the southern end of the project corridor. 

Click on the map to view the flyer depicting exact location of lane closures.

Description

Traffic management ahead of major construction to safely install contraflow: lane two closure on the existing dual carriageway for approx. 1km at the Northern end and 3km at the Southern end of the project corridor; contraflow running on this area. 

Date and time:

Closure of lane two on existing dual carriageway from Thursday 3 April 2025 for approximately 15 days, 24 hours a day.  

From Friday 25th April 2025 contraflow running will remain in place on these areas of the existing dual carriageway for approximately 1km at the northern and 3km at the southern ends of the project. The contraflow will then transition into the narrowed lanes on the single carriageway along the project corridor before rejoining the dual carriageway via contraflow.